Hurst Portfolio_Case Studies_Retail - Flipbook - Page 42
Project_Escalator Removal
Sector_Shopping Centre
Hurst was tasked with removing an
escalator from an empty unit in a popular
shopping centre in West London, including
infilling pits and penetration creating,
ensuring a clean and ready-to-design
space for the new resident, Sephora.
The project faced several challenges due
to its location in a busy retail complex with
the potential to disrupt public services and
accessibility.
BEFORE:
42.
Hurst ensured clear communication
with the shopping centre management
throughout the process so the public could
be kept informed. Work was scheduled
outside of hours to shield the public from
ongoing work and temporary hoarding
was installed around the perimeter,
providing safe navigation around the site.
The scope of works included:
»
Removal and repurpose of rear doors
»
Installation of double door sets
(hoarding and new B.O.H location)
»
Isolation/disconnection of M&E
services
»
Removal of walls and units to level 55
»
Extraction of ductwork system
»
Commissioning, validations & BMS
reset of control damper
»
New and removal of steelwork
»
»
»
»
»
»
Void former infill to lift shaft
Escalator pit and lift infills
Additional openings
Temporary propping (local acrows),
handrails, safety harness & lanyard
MEWPs access
Works scheduled out of hours